Wayne, NJ
January 2025
New Construction Second-Floor Deck Railings
Project Overview
Second-floor deck aluminum railings installed during the final exterior phase of a new-build home, coordinated with the GC schedule.
Analysis
We timed the install between siding and paver completion to avoid damage. All anchors were pre-blocked by the framer.
Process
Pre-build coordination, fabricate, one-day install.
Outcome
A railing install that fit cleanly into the build schedule and passed final inspection.
Project Details
Materials Used
6063-T6 aluminum, decorative scroll inserts, satin-black powder coat, structural lag bolts into framing blocking.
Methods & Techniques
Pre-blocked framing coordination, lag-bolt install, sealed penetrations.
Key Highlights
Pre-blocked framing, decorative scroll inserts, builder-coordinated schedule.